END Client
Stoke City Council
Services
3D CAD, M&E Install
Design & Installation of E125kW CHP
We provided 3D design, Mechanical & Electrical installation to E125kW Combined Heat & Power system at Fenton Leisure Centre in Stoke.
- CDM Responsibilities
- Shared Design Responsibility
- Pipework, Ventilation & Electrical Installation
- Bespoke Fencing Fabrication & Powder Coating
- Accident Free, On Time & On Budget
3D Co-Ordinated Layout
We produced 3D co-ordinated designs for the client for approval before going to fabrication.
M&E Installation
All services including, exhaust system (Stainless Steel, LTHW (Low Carbon Steel), ventilation and electrical system were installed by our on site operatives.
Project Completion!
We completed the project without any Health & Safety incidents and spent just 17 days on site, due to our off site fabrication process.
The end result was the client was happy and now has a great low carbon technology producing heat & power to be consumed on site at the leisure centre.
0
Installed in just 17 days due to our off-site fabrication process.
20
Installed without any accidents or safety incidents.